Construction progress updated in August 2022 – Project of Repairing damage to foundation, road surface, drainage system and traffic safety at section Km51+600 - Km53+500; Km57+00 - Km59+700, National way 47, Thanh Hoa province
In August, 2022, INVESTCORP Land Thanh Hoa Company Limited focused on speeding up the construction progress and basically completed the items such as construction of road mold excavation, compaction, reinforcement and expansion of roadside, and spreading crushed stone to widen the roadside.
In addition, the repair of the drainage system which is being implemented by INVESTCORP Land Thanh Hoa in parallel includes excavation, transportation and installation of concrete drainage structures. By the end of August 2022, the total estimation of completed volume is 24%.
As planned in September 2022, INVESTCORP Land Thanh Hoa will continue to speed up the construction progress of works related to road surface and drainage system.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED