Construction progress updated in August 2021 – Yi Da Garment Factory Project Phase 3 - Canteen & Motorbike parking
On June 10, 2021, the Yi Da Garment Factory Project Phase 3 - Canteen & Motorbike parking of Yi Da Vietnam Limited was commenced at Song Thao Industrial Complex, Cam Khe town, Cam Khe district, Phu Tho province. The Canteen & Motorbike parking is built with a 3-storey open space design, a total floor area of 7,140m2 and a building height of 11.35m.
At the end of August 2021, INVESTCORP Dong Minh has completed the construction of floor beams on the 3rd floor, the 2nd and 3rd floors’ stairs, columns on the 3rd floor and floor beams of the ramp. The safety railing, wall construction and surface fixing of floor beams are being implemented.
In September 2021, INVESTCORP Dong Minh will fabricate and erect steel structures; install corrugated iron roof, safety railings; build, plaster and paint walls and stairs; grind and fix surface of floor beams and construct doors and windows.
It is expected that the Canteen – Motorbike parking will be completed and put into use in October 2021.

- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa