Construction progress updated in April 2023 – An additional tender package under item "Finish construction and installation of office furniture" of project "Manufacture of hot and cold packs and high-class cardiac electrode pads – Intco Medical”
In April 2023, INVESTCORP 15 completed painting the outside beams and columns and handed them over to the construction unit erecting the outside glass wall to continue implementing the following works; the erection of the steel frame reinforcing drywall system has also been completed.
Along with that, the works such as the erection of drywall steel frames, drilling of bare bones, erection of drywall sheets, screeding floors, paving stairs, and installing underground electrical conduits and wall electrical conduits, and inside skim-coat work were also completed by INVESTCORP 15 over 50% of the volume
It is expected that in May 2023, INVESTCORP 15 will complete the installation of conduits, electric wires, drywalls, the installation of curtains, paving stairs, and WC as well as the implementation of the next works.It is expected that in May 2023, INVESTCORP 15 will complete the installation of conduits, electric wires, drywalls, the installation of curtains, paving stairs, and WC as well as the implementation of the next works.

- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa