Construction progress updated in April 2023 – An additional tender package of "Detention basin to store after-treatment water" under "Textile and Garment Factory Project of Ramatex Nam Dinh- Phase 1"
At the beginning of April 2023, INVESTCORP 15 implemented the construction of the additional tender package under the "Textile and Garment Factory Project of Ramatex Nam Dinh- Phase 1".
By the end of April 2023, the Company has completed the excavation of the lakebed and the removal of waste soil. Besides, the cavity stone building has reached 90% of the volume and the sand filling of the lake bed has reached 95% of the volume. The spillway separating Lake 1 and Lake 2 was also demolished.
It is expected that in May 2023, INVESTCORP 15 will continue to complete the remaining volumes such as building cavity stones, filling the lakebed with sand, air drainage at the lake bottom, spreading GCL sheets, spreading HDPE sheets and concrete to block HDPE sheets. At the same time, the construction of the pump house will also be implemented in parallel.


- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa





